External work

In the week of the 9th of November work had started on the wooden cladding for the walls. The windows had also been put in place, although boarded up to protect them from the local youth's hooliganism:

PIC09112.JPG (218920 bytes)     PIC09113.JPG (162928 bytes)     PIC09116.JPG (167246 bytes)     PIC09117.JPG (146213 bytes)

18th of November:

PIC18111.JPG (132686 bytes)     PIC18112.JPG (217199 bytes)     PIC18113.JPG (170012 bytes)     PIC18115.JPG (191609 bytes)

On the 24th of November the roof had also been prepared for the slate:

PIC24111.JPG (196349 bytes)     PIC24112.JPG (165484 bytes)     PIC24113.JPG (199437 bytes)     PIC24114.JPG (172832 bytes)     PIC24115.JPG (137520 bytes)

On the 7th of December a large part of the slate had been fixed on the roof and the chimney had been installed:

PIC071212.JPG (104268 bytes)     PIC071213.JPG (143702 bytes)     PIC071214.JPG (165059 bytes)     PIC071219.JPG (116920 bytes)

On the 15th of December solar cells had been installed! Hurray!!!

PIC15123.JPG (137650 bytes)     PIC15124.JPG (170896 bytes)     PIC15121.JPG (162168 bytes)     PIC15122.JPG (149882 bytes)

Most of the external work had been completed on the 21. of December, so a large part of the scaffolding could be removed:

PIC21121.JPG (128859 bytes)     PIC21123.JPG (139826 bytes)     PIC21129.JPG (151389 bytes)

The conservatory finally started to take form from week 4 in January:

PIC2601021.JPG (157862 bytes)     PIC2601023.JPG (179374 bytes)     PIC2601024.JPG (148811 bytes)     PIC0102026.JPG (166607 bytes)     PIC02020221.JPG (144115 bytes)

On the 15th of February the glass has been placed in the conservatory, the outside doors have been hung and the cladding has been finished.